PROJECT OVERVIEW


Client: Trustpower Ltd
Location: Mangorei Power Station
Scope of Work: Bore alignment and correction
Date: June 2016

As part of a refurbishment, AEG was asked to perform bore alignment measurement and correction on the G2 unit at Mangorei Power Station.

The work was undertaken using Pruftechnik's BORALIGN system. Custom bracketry was required to complete measurement.

Measurement resulted in shimming of several of the elements through the bore. The result was an accurate alignment throughout - from the stator through to scroll case.